Dec 17, 2018

20 West Apartments Update

Building is taking form, 2nd and 3rd floor steel erection is ongoing with 1st floor CMU walls complete. 4th and 5th floor steel is scheduled to be erected after the first of the year. Electrical service/transformer has been installed. Coming months will bring completion of the steel erection, placing of the concrete decks and exterior framing being installed.